Domite®/Laminite® Grizzly Cassettes Reduce Plant Down time
The miner saved 38% in annual costs, as well as saving on shutdowns.
Background
Location
South Africa
Commodity
Iron Ore
Wear Product
Grizzly Cassettes
The Challenge
- Maintenance costs and down time – Grizzly Deck change out takes 6 days per year, competitor solution only lasted 16 weeks.
- Eliminate safety JSA work.
- Reduce maintenance on a Grizzly Cassette Deck.
The Solution
Replace competitor solution with Domite Grizzly Cassette Deck.
Benefits of Domite grizzly cassettes
The Impact
- Domite Grizzly Cassette Decks lasted 9 million tonnes.
- Plant down time for wear plate change outs is now 2 days per annum.