Background
Location
South Africa
Commodity
Iron Ore
Wear Product
Rockbox Liners
The Challenge
- Maintenance costs and down time – mining wear product change out is 21 days per annum – Nihard plates only lasting 127, 000 tonnes.
- Eliminate confined space work.
- Reduce maintenance on tip pocket conveyor chute.
The Solution
Replace Nihard with Domite/Laminite Rockbox liners.
Benefits of Domite/Laminite rockbox liners.
The Impact
- Domite rockbox liners lasted 3 million tonnes.
- Plant down time for wear plate change out is now 1 day per annum.